Project – Storm Jameson West Building, Leeds University
Client – Leeds University
Location – Leeds
Materials – Sika
About the project:
We were called into Leeds University to address a 90m2 podium deck area which was allowing rain water ingress into one of the Universities internal walkways after numerous attempts had already failed.
After the paving slabs in the area were removed we prepared the podium deck, ensuring any further defects uncovered were repaired using a fast setting waterproof mortar. Once moisture levels within the mortar had been checked Sika Balcon 20 buried system was applied comprising of the primer, the base with remat and finally the top coat.
Upon completion the area received a successful flood test before the paving slabs were replaced.
The Sika Balcon 20 system provided the client with the 20-year Sika guarantee.
Project – Storm Jameson West Building, Leeds University
Client – Leeds University
Location – Leeds
Materials – Sika
About the project:
We were called into Leeds University to address a 90m2 podium deck area which was allowing rain water ingress into one of the Universities internal walkways after numerous attempts had already failed.
After the paving slabs in the area were removed we prepared the podium deck, ensuring any further defects uncovered were repaired using a fast setting waterproof mortar. Once moisture levels within the mortar had been checked Sika Balcon 20 buried system was applied comprising of the primer, the base with remat and finally the top coat.
Upon completion the area received a successful flood test before the paving slabs were replaced.
The Sika Balcon 20 system provided the client with the 20-year Sika guarantee.